March 1st, 2004 - foundation walls forms in

December 30: Sign Purchase Agreement
January 9: House Placement Staked
January 12: Options Due
February 23: Preconstruction Meeting
February 25: Groundbreaking
February 27: Foundation Footers
February 29: Footers with Gravel
March 1: Foundation Wall - forms
March 3: Foundation Walls - pour
March 4: Foundation Walls - done
March 8: Plumbing and First Grading
March 13: Basement Floor Poured
March 19: Basement Walls
March 20: First Floor
March 22: Interior First Floor
March 23: Second Floor
March 24: Roof Trusses
March 26: Walkthrough
March 28: Random Visit
April 5: Brick
April 9: Pre-drywall Inspection
April 12: Inspector Visit
April 23: Brick Done
April 25: Drywall in Progress
May 2: Vinyl Flooring In
May 4: Rear Siding On
May 7: Cabinets In
May 15: Brick Is Clean
May 18: Finishing Touches
May 23: Carpet In
 
 
House: concrete forms in
It rained pretty much all day today while the guys were out there putting in the concrete forms for our basement foundation. They were so friendly and nice... so far everyone working on the house has been. They said that the concrete will be poured tomorrow afternoon at 2:00, so I'll be there.

I'd like to take them cookies... because they were working in the rain all day. But I don't think that I can keep up making cookies twice a week, which seems to be as often as the crews turn over. They are all subcontractors. If I could just make cookies for them when it was a particularly bad day for working on the house, I think it would be nice. But I can't keep that up for four months.