December 30: Sign Purchase Agreement
January 9: House Placement Staked
January 12: Options Due
February 23: Preconstruction Meeting
February 25: Groundbreaking
February 27: Foundation Footers
February 29: Footers with Gravel
March 1: Foundation Wall - forms
March 3: Foundation Walls - pour
March 4: Foundation Walls - done
March 8: Plumbing and First Grading
March 13: Basement Floor Poured
March 19: Basement Walls
March 20: First Floor
March 22: Interior First Floor
March 23: Second Floor
March 24: Roof Trusses
March 26: Walkthrough
March 28: Random Visit
April 5: Brick
April 9: Pre-drywall Inspection
April 12: Inspector Visit
April 23: Brick Done
April 25: Drywall in Progress
May 2: Vinyl Flooring In
May 4: Rear Siding On
May 7: Cabinets In
May 15: Brick Is Clean
May 18: Finishing Touches
May 23: Carpet In
Photos
1st Floor
Kitchen
Morning Room
Family Room
Study
Dining Room
Living Room
Mud Room
Powder Room and Foyer
2nd Floor
Master Bedroom
Sitting Room
Master Bathroom
Play Room
Bedroom #2
Bedroom #3
Bedroom #4
Bathroom #1
Bathroom #2
[an error occurred while processing this directive]
www.whitedoom.com
Last modified: January 3, 2007
Visitors:
26,066