May 15th, 2004 - brick has been cleaned

December 30: Sign Purchase Agreement
January 9: House Placement Staked
January 12: Options Due
February 23: Preconstruction Meeting
February 25: Groundbreaking
February 27: Foundation Footers
February 29: Footers with Gravel
March 1: Foundation Wall - forms
March 3: Foundation Walls - pour
March 4: Foundation Walls - done
March 8: Plumbing and First Grading
March 13: Basement Floor Poured
March 19: Basement Walls
March 20: First Floor
March 22: Interior First Floor
March 23: Second Floor
March 24: Roof Trusses
March 26: Walkthrough
March 28: Random Visit
April 5: Brick
April 9: Pre-drywall Inspection
April 12: Inspector Visit
April 23: Brick Done
April 25: Drywall in Progress
May 2: Vinyl Flooring In
May 4: Rear Siding On
May 7: Cabinets In
May 15: Brick Is Clean
May 18: Finishing Touches
May 23: Carpet In
 
 
 
 
 